    Comprehensive plan issued for Beijing's new airport

    1
    2018-07-06 15:20:07chinadaily.com.cn Editor : Li Yan ECNS App Download
    An aerial photo shows the construction site of Beijing's new airport in southern Daxing district in Beijing. The new international airport is taking shape and already has a roof in March. (Photo by Yang Zhiyong/chinadaily.com.cn)

    An aerial photo shows the construction site of Beijing's new airport in southern Daxing district in Beijing. The new international airport is taking shape and already has a roof in March. (Photo by Yang Zhiyong/chinadaily.com.cn)

    The acceptance check for Beijing's new airport and auxiliary projects has been set for June 30, and three months later, the airport will be put into operation on Sept 30, 2019, according to a comprehensive plan issued Friday.

    The comprehensive plan issued at a meeting covers the leftover construction work of the airport, the acceptance check work, transfer plan, preparatory work for formal operations, reception plan and other relevant special plans.

    Feng Zhenglin, head of the Civil Aviation Administration of China, said at the meeting Friday that the plan has set some important time frames for the new airport project to be put into operation on schedule.

    The new airport north line expressway will be available for traffic in December, the ground refueling facilities should be ready in April, and the new airport expressway will be ready for traffic in June.

    When the new airport is in operation, the core work area, life service area, freight area and supporting facilities in the first phase should be in use for China Eastern Airlines and China Southern Airlines.

    The Beijing-Xiongan intercity high-speed railway should be operational. Meanwhile, the new subway line linking downtown Beijing and the airport, the new airport expressway and north line expressway should all be in use.

    Authorities have urged related units to push ahead with construction work and preparatory work for operations at the same time. Some 92 percent of the flight area and 42 percent of road projects have already been finished.

    The terminal has been completed, and interior decoration and equipment installation are underway. The west air control tower will be finished in June, and construction of the east tower is pushing forward.

    Related units are urged to push ahead with work on personnel training, management mode research, organizational structure research, aviation business research and the compilation of an airport handbook.

      

    Related news

    MorePhoto

    Most popular in 24h

    MoreTop news

    MoreVideo

    News
    Politics
    Business
    Society
    Culture
    Military
    Sci-tech
    Entertainment
    Sports
    Odd
    Features
    Biz
    Economy
    Travel
    Travel News
    Travel Types
    Events
    Food
    Hotel
    Bar & Club
    Architecture
    Gallery
    Photo
    CNS Photo
    Video
    Video
    Learning Chinese
    Learn About China
    Social Chinese
    Business Chinese
    Buzz Words
    Bilingual
    Resources
    ECNS Wire
    Special Coverage
    Infographics
    Voices
    LINE
    Back to top Links | About Us | Jobs | Contact Us | Privacy Policy
    Copyright ?1999-2018 Chinanews.com. All rights reserved.
    Reproduction in whole or in part without permission is prohibited.
    主站蜘蛛池模板: 呈贡县| 炎陵县| 陆良县| 徐水县| 射洪县| 临朐县| 岫岩| 安徽省| 兴仁县| 磴口县| 鸡东县| 瓦房店市| 临清市| 涡阳县| 抚州市| 如东县| 望奎县| 闻喜县| 迭部县| 曲松县| 那曲县| 六盘水市| 彭泽县| 肥乡县| 剑河县| 浙江省| 南华县| 文成县| 张掖市| 浏阳市| 呼伦贝尔市| 怀仁县| 新津县| 星座| 柘荣县| 赫章县| 马公市| 孟连| 绥中县| 双鸭山市| 台州市|