    10,000 workers finish railway modification in Liaoning in 24 hours

    1
    2021-05-31 17:37:07Ecns.cn ECNS App Download

    (ECNS) -- The Chaoyang-Jinzhou High-speed Railway was successfully connected to the newly built Linghai South Station in Liaoning Province on Thursday.

    It took over 10,000 workers less than 24 hours to complete the modification project. The transportation capacity of the Qinhuangdao-Shenyang section of Beijing-Harbin Railway has been strengthened, too. This is the largest scale, on-spot work on a Chinese railway ever.

    The project was carried out from 6 am, May 26 to 5 am, May 27 in Qinhuangdao-Shenyang section. More than 12,000 workers and over 500 sets of large mechanical equipment took part in the construction.

    Modifications will ensure the timely operation of Chaoyang-Jinzhou railway within 2021. It has shortened the travel time between cities in southeast Liaoning to Beijing.

    MorePhoto

    Most popular in 24h

    MoreTop news

    MoreVideo

    LINE
    Back to top Links | About Us | Jobs | Contact Us | Privacy Policy
    Copyright ©1999-2021 Chinanews.com. All rights reserved.
    Reproduction in whole or in part without permission is prohibited.
    主站蜘蛛池模板: 麻城市| 乐昌市| 宿松县| 江孜县| 察雅县| 新建县| 福建省| 琼海市| 胶州市| 都江堰市| 额尔古纳市| 永寿县| 凉城县| 开鲁县| 延寿县| 云和县| 济阳县| 淮滨县| 江山市| 牙克石市| 清水河县| 平乡县| 中西区| 广东省| 凤阳县| 邵武市| 离岛区| 太和县| 文化| 苍溪县| 南通市| 卓尼县| 平原县| 蒙自县| 泽州县| 海林市| 高安市| 江西省| 仙桃市| 溆浦县| 红安县|