LINE

    Text:AAAPrint
    Economy

    Jakarta-Bandung high-speed rail project gets all permits

    1
    2016-08-22 09:24Global Times Editor: Li Yan
    Graphics: GT

    Graphics: GT

    Project could be completed within three years: experts

    Seven months after ground was broken for Indonesia's first high-speed railway, which is being developed by a China-Indonesia joint venture, the project received a construction permit for its entire length, media reports said Sunday.

    Experts said Sunday that construction should be completed within three years as planned, -despite concerns that work might be delayed.

    Domestic news portal caixin.com reported on Sunday that the developer of the Jakarta--Bandung high-speed rail project, PT Kereta Cepat Indonesia China (KCIC), recently received a construction permit that covers the entire 142 kilometers line. The portal cited sources from China Railway Corp (CRC).

    KCIC is a consortium consisting of CRC and four Indonesian state-owned companies.

    The source told Caixin that work on the line has been progressing as planned, with absolutely no possibility of a halt, and the person noted that the Ministry of Transportation of Indonesia now lists the railway as a high-priority project.

    But construction of the railway linking -Jakarta and Bandung, the largest and third-largest cities in Indonesia, has been hindered by licensing woes.

    After the ground-breaking ceremony on -January 21, KCIC only had a permit to work on a section of 5 kilometers. By the end of June, the permit covered just 56.8 kilometers, or two-fifths of the entire length of the railway, -according to Caixin.

    The Jakarta-Bandung high-speed railway, with a maximum designed speed of 350 kilometers per hour, will reduce travel time between the two cities to 40 minutes from more than three hours at present and is planned to be completed in three years, according to the CRC.

    Although permits have been slower in coming than expected, KCIC can finish the project within three years, experts said.

    "The consortium is capable of finishing the project within 18 months, and it took into consideration that some delays might occur during the construction phase," Wang Mengshu, -academician at the Chinese Academy of -Engineering, told the Global Times on Sunday.

    Land acquisition, another factor affecting the progress of the project, should also go smoothly, Xu Liping, a research fellow from the National Institute of International Strategy at the Chinese Academy of Social Sciences, told the Global Times on Sunday.

    "The majority of the land the railway will run through belongs to state-owned firms in Indonesia, with private land accounting for only a small part, so land acquisition should be relatively easy," Xu said, noting that the developer must pay close attention to coordination during construction work.

    Differences between the national conditions of the two countries and their respective cultures should be observed, Xu said.

    "The developer should also work seamlessly with local partners and abide by local laws. It should also formulate emergency action plans, including those covering security. These approaches can help safeguard construction of the railway to make progress according to its agenda," Xu said.

    The construction of the railway is expected to create 40,000 jobs a year in Indonesia, according to media reports.

    In March, KCIC was granted the right to operate the Jakarta-Bandung railway line for 50 years, starting from May 31, 2019.

    The project is set to cost $5.13 billion.

      

    Related news

    MorePhoto

    Most popular in 24h

    MoreTop news

    MoreVideo

    News
    Politics
    Business
    Society
    Culture
    Military
    Sci-tech
    Entertainment
    Sports
    Odd
    Features
    Biz
    Economy
    Travel
    Travel News
    Travel Types
    Events
    Food
    Hotel
    Bar & Club
    Architecture
    Gallery
    Photo
    CNS Photo
    Video
    Video
    Learning Chinese
    Learn About China
    Social Chinese
    Business Chinese
    Buzz Words
    Bilingual
    Resources
    ECNS Wire
    Special Coverage
    Infographics
    Voices
    LINE
    Back to top Links | About Us | Jobs | Contact Us | Privacy Policy
    Copyright ©1999-2018 Chinanews.com. All rights reserved.
    Reproduction in whole or in part without permission is prohibited.
    主站蜘蛛池模板: 遵义县| 华坪县| 汉沽区| 浙江省| 寿光市| 德江县| 文水县| 卢氏县| 赞皇县| 南汇区| 海口市| 西乌| 秭归县| 平南县| 秀山| 屯留县| 南和县| 朝阳县| 林口县| 永清县| 安龙县| 蓝田县| 河源市| 大丰市| 邢台市| 沾益县| 渑池县| 饶河县| 乌鲁木齐县| 乌拉特中旗| 大宁县| 瑞丽市| 福清市| 奎屯市| 株洲县| 安西县| 如东县| 启东市| 中牟县| 汨罗市| 申扎县|